Roof Installation
Wednesday 21st - Tuesday 27th September 2005 -- Second/final layer render added to rear of building. Internal partition walls begun. Stairwell opening to second floor increased from 1000mm to 1100mm. Lighting designer employed. Deciding on exterior colour. Finalising position of toilets on second floor.
Tuesday 20th September 2005 -- Beading being added around all external windows [ Photo ].
Monday 19th September 2005 -- First layer scratch-coat render applied to external front wall. Removal of iron external rear staircase [ Photo ].
Friday 16th September 2005 -- First layer scratch-coat render applied to external back wall. Completion of window installation. Roof complete [ Photos ].
Thursday 15th September 2005 -- Windows fitted to first and second floors, including two arched windows.
Wednesday 14th September 2005 -- Coping stones added.
Tuesday 13th September 2005 -- Ridge tiles being put in place at apex of roof. Lead flashing continuing. Roof now completely tiled.
Thursday 8th September 2005 -- Windows have arrived, including the two all-important arched windows. Slating of the roof continues [ Photos ].
Wednesday 7th September 2005 -- Velux roof windows installed.
Tuesday 6th September 2005 -- Eternit fibre cement slates being added to roof.
Monday 5th September 2005 -- Roofing felt and battens added.
Tuesday 30th August - Friday 2nd September 2005 -- Lead flashing added. Gutter installation completed.
Friday 26th and Thursday 25th August 2005 -- Working on the woodwork to support the guttering. Photos of loft space available.
Wednesday 24th August 2005 -- Additional noggins being added to brace roof and flooring.
Tuesday 23rd August 2005 -- Rear gable end wall being built up to final height.
Monday 22nd August 2005 -- Front and middle built sections of roof being built. Cross-bracing of rafters being added.
Friday 19th August 2005 -- Continuation of roof carpentry.
Thursday 18th August 2005 -- Continuation of roof carpentry. Getting more difficult to take 'overview' photos now that the floor is back in between the first and second floors.
Wednesday 17th August 2005 -- Continuation of roof carpentry.
Tuesday 16th August 2005 -- Installation of roof trusses virtually completed. Centre 'built' roof section (around staircase) began.
Monday 15th August 2005 -- Intallation of the roof trusses begins [photo].
Friday 12th August 2005 -- 35 tonne Crane hoists trusses into the building [photo].
Wednesday 10th August 2005 -- Cutting of scaffold to allow entry of trusses; continuation of rear gable-end wall; preparation for truss hoist on Friday.
Tuesday 9th August 2005 -- Survey by crane company to hoist trusses into position.
Saturday 6th August 2005 -- 7am trusses arrive on the back of an articulated lorry [photo]. It's great to get a sense of the size of the loft room [photo].
|