4-6 Station Approach is a mixed-use (shops and offices) commercial property directly outside the train station at Ashford, Middlesex.
The building was originally built in 1907 and used and owned by a furniture retailer and auctioneer. The building was rebuilt in 2005-2006, adding a new second floor office space with arched windows.
> Click here for the Before and After photos
> Click here for the Diary
Stage 3 - Refurbishment of office, 4 Station Approach Jan - Mar 2006
Preparation
- Complete gut the interior back to bare brick [ Done ]
- Build rear wall, with new 1000x800 frosted window [ Done ]
- Knock through 6 foot opening under stairs [ Done ]
- Removal of false ceiling (steel lintel) [ Done ]
- Minor damp treatment [ Done ]
Internal Work
- Plasterboard/plaster all walls [ Done ]
- Installation of wooden flooring throughout [ Done ]
- Install bathroom and kitchenette [ Done ]
- Installation of compact flourescant downlights; skirting trunction with double-data sockets; shelving; data/secure walk-in cupboard [ Done ]
External Work
- Complete replacement of front windows [ Done ]
- Make good and paint signage area (including power outlet) [ Done ]
- Render and paint lower half of rear exterior wall [ Done ]
- Render and paint side of shop and office [ Done ]
Agreement: 8th Dec 2005
Completion deadline: 31st Mar 2006
Actual completion: 16th Mar 2006
Tenant lease commencement: 1st Mar 2006
Tenant occupation: 15th May 2006
Building now fully let and complete.
Stage 2 - Internal Work, 4-6 Station Approach Oct 2005 - Dec 2005
- Installing floor for second floor [ Done ]
- First floor partitions [ Done ]
- First fix electrical installation [ Done ]
- Battening and plasterboard throughout [ Done ]
- Plastering throughout [ Done ]
- Install two staircases (ground-to-first floor, first-to-second floor) [ Done ]
- Replacing flooring on first floor [ Done ]
- Plumbing and washroom installation
- Decoration of office suites. [ Done ]
- Second fix electrical installation. [ Done ]
- Builders finish - Friday 16th December 2005. [ Done ]
- Carpet throughout - Monday 19th - Tuesday 20th December 2005. [ Done ]
- Tenant occupation (first floor) - Wednesday 21st December 2005 (10 days early). [ Done ]
- Tenant occupation (secondfloor) - Wednesday 21st December 2005. [ Done ]
Completion deadline: 23rd Dec 2005
Actual completion: 20th Dec 2005
Tenant Occupation: 21st Dec 2005
Stage 1 - External Work, 4-6 Station Approach Jul - Sep 2005
Work began on Monday 4th July 2005 on the redevelopment of the upper floors of the building. A number of 'enabling works' had already been completed, including party wall agreements and trial holes to expose foundations.
- Erection of scaffold 'tin hat' to entirely cover the building [ Done ]
- Clearing of everything in the first floor (including wall partitions and ceilings) [ Done ]
- Removal of roof [ Done ]
- Building up gable end walls by 600mm (requiring unanticipated total gable end rebuild for first and second floors) [ Done ]
- Installing roof trusses [ Done ]
- Install roof windows [ Done ]
- Install roofing [ Done ]
- Replacement of existing first-floor windows and addition of second floor windows, front and back [ Done ]
- Removal of rear external iron staircase [ Done ]
- Rendering gable ends, front and back, including lintel detail [ Done ]
- Paint exterior (including lintels) [ Done ]
- Removal of scaffold [ Done ]
Work started: 4th July 2005
|